June 2026 Newsletter
Deliveries of the over-sized loads to build the five turbines in the southern end of site (via Babylon Coast Road) are complete.

Turbines: 12 Vestas V162, 6.4MW
Turbine tip height: 206m
Tower height: 125m
Rotor diameter: 162m
Transmission Connection: 66kV from wind farm to Dargaville substation
Investment: NZ$287m
Expected annual generation: 221 GWh
Kaiwaikawe is Northland’s first wind farm, located 12km north-west of Dargaville and 3km inland from the Tasman Sea. The $287 million wind farm has 12 turbines arranged in two clusters: seven in the north and five in the south.
Its Vestas V162-6.4MW turbines are the first of their kind installed in New Zealand and the largest and tallest wind turbines in Aotearoa.
The wind farm connects to Northpower’s substation near Dargaville, then to the national grid at Maungatapere.
Construction began in January 2025, with electricity first generated in July 2026. All 12 turbines are now installed. Final commissioning, testing, site rehabilitation and removal of construction facilities will continue through to early 2027.
Once fully commissioned, the wind farm is expected to generate 221 GWh of renewable electricity a year — enough to power more than 31,000 average New Zealand homes.*
We celebrated the official opening of Northland’s first wind farm on 23 November 2026, alongside mana whenua Te Roroa, landowner Pāmu, community representatives and project partners. The ceremony recognised the people and partnerships that brought Kaiwaikawe Wind Farm to life. Read more about the opening celebration.

Community
We've set up a Community Consultative Group to meet regularly and be a point of contact for local residents. We are committed to listening to you and working with you to ensure community issues are addressed. If you’re interested in joining this group, please let us know by email.
Please email us at kaiwaikawewindfarm@mercury.co.nz with any questions or to sign up for regular project updates.
* Based on average household electricity use of 7,000 kWh a year.
Deliveries of the over-sized loads to build the five turbines in the southern end of site (via Babylon Coast Road) are complete.
Works at ground level and below are nearing completion.
The transport route upgrades that were needed for the big loads are now complete.
Turbine foundations complete.
Internal roading is largely complete in the South of site, and access to the northern turbine positions is being progressed.
We officially ‘broke ground’ with a ceremony on 27 March.
The project is on track to receive the first turbines next autumn.
This complex project takes a big team (at the height of construction there will be up to 100 people on site each day).